Our Besser Block Wall Construction Process
The strength of a Besser block wall comes from the steel and concrete inside it, so most of what matters happens before the wall looks finished. Here's the sequence our crew works to.
Engineering and design — footing size, block width, bar diameter and spacing all get specified for your retained height and soil.
Footing excavation and pour — we dig the footing trench and pour a reinforced footing with starter bars left standing in position.
Block laying — blocks are laid in courses, threaded over the starter bars, and kept plumb and level as the wall rises.
Horizontal reinforcing — bond beam bars go in at the spacings the engineer calls for, tying the wall together across its length.
Core filling — cores are filled with concrete and compacted so there are no voids left around the steel.
Drainage and finishing — drainage metal, base pipe and outlets go in behind, then we plaster, paint or leave the face as specified.